Claim Settled Against Printing Plant
A claim was settled against a design/build firm for $24 million alleging various defects and deficiencies in a newly constructed printing plant. Initial allegations of damage were $300 million. Problems arose with the concrete, fire protection, electrical, and HVAC systems. The client continues to incur costs to repair the defects. The design/build contractor sought recovery of $5 million from various subcontractors based on their presumed liability for construction errors that contributed to the defective conditions at the printing plant.
This is a claim scenario developed from a single claim or several claims and has been developed for illustrative purposes only.