Design-Builder Unsuccessful in Suit against Engineering Subconsultant for Cost Overruns. Preliminary Drawings Can’t be Expected to be as Precise as Final Documents

Source: https://www.constructionrisk.com/, January 2020
Design-Builder of a bridge sued its engineer subconsultant for costs allegedly attributed to errors in preliminary designs and cost/quantity estimates provided under the terms of a Teaming Agreement. Following a bench trial, the court rejected most of the design-builder’s claims, finding that the contractor was essentially attempting to argue that the preliminary plans prepared for bidding purposes should have been complete and accurate to the same extent as if they were one hundred percent final construction documents. Design-Builder claimed that if the engineer had not breached the Teaming Agreement it would have bid more and made a greater profit. There was no evidence that the engineer failed to meet the standard of care for preliminary design documents and nothing suggested anything the engineer did caused the Project to be more expensive. Middlesex Corp., v Fay, Spofford & Thorndike, Inc., 2019 WL 3552609, (Superior Court of Massachusetts, Suffolk County, 2019). Read more.

Find a Broker or Underwriter

Search by product, location or name
https://premium.insurancebusinessmag.com/us-iba-5-star-wholesale-brokers-and-mgas-2026-rt-specialty/p/1https://partners.wsj.com/most-loved-workplace/most-loved-workplaces-2025/americas-top-100-most-loved-workplaces/https://premium.insurancebusinessmag.com/us-iba-top-insurance-employers-2026-ryan-specialty/p/1

Please Update Your Browser

Unfortunately Microsoft is no longer providing support or security fixes for your web browser. RT Specialty values the safety and security of its clients’ data, and as such this site requires the use of a modern web browser. To update your web browser, please see the links below. If you have any questions or would like additional information, please email info@rtspecialty.com or call (312) 784-6001.

Firefox Firefox Chrome Chrome IE Internet Explorer Edge Microsoft Edge