A street and road contractor was responsible for repaving a major highway that was adjacent to a creek. At the end of the day, a tack coat was sprayed onto theĀ sub-base prior to paving activities, which were to commence the following day. An overnight thunderstorm washed the tack coat into the adjacent creek. TheĀ contractor did not follow best practices or the manufacturerās recommendations for the application of the tack coat. The cleanup of the creek and expenses for Natural Resource Damages exceeded $200,000.