A worker was seriously injured during construction by a collapsing wall. In his lawsuit, he alleged that the general contractor/construction manager was negligent for failing to provide for safety precautions. The courts agreed and held that the general contractor/construction manager was responsible for inspecting continuously or supervising the work of the subcontractors, including the right […]
A contractor subcontracted the design of a ventilation system to a mechanical engineer. The engineer miscalculated the cooling needs of the building and specified an inadequate ventilation system. Because of the system’s poor performance, the building owner demanded $180,000 to replace it. At the time of the claim, the mechanical engineer had let his Errors […]
After purchasing an apartment complex in Texas from the original builder/developer, the plaintiff  claimed that the property had a number of construction defects. The plaintiff sued the builder/developer as well as a number of other parties who were involved in the design and/or construction of the residence. After a significant amount of discovery, the defendants developed […]
A contractor retained an architect for a school project who provided a certificate of insurance showing a $3 million limit of liability. During construction, a design defect was discovered that delayed the project for several months. The school district was forced to rent portable classrooms and filed for substantial damages against the contractor. Although the […]
A construction manager was hired to construct a condominium project. Water infiltration occurred around the windows that was caused by defective construction including the improper installation of flashing. Accusations were made for negligent construction management. Five million dollars in damages were sought. This is a claim scenario developed from a single claim or several claims […]
A claim for an at-risk construction management firm arose during extensive renovation and abatement at a school. The construction manager hired a firm to estimate the levels of asbestos in school. The claimant alleged that the level of asbestos was grossly underestimated resulting in an additional $13 million during construction to abate asbestos. This is […]
Source: Politics Daily As the rates of learning disabilities, autism and related conditions rise, the Environmental Protection Agency is preparing to release a roster of the pollutants likely to contribute to these or other neurological disorders. In an ongoing, three-year effort, an EPA team has determined which developmental neurotoxicants — chemicals that damage a fetal […]
A construction firm performed At-Risk Construction Management services to widen a 100 mile two-lane highway. The insured subcontracted the construction management and engineering services.  The claimant alleged pavement heaves, inadequately compacted fill holes, settlement, sink holes, and depression on the bridge decks. The claimant sought costs for necessary repairs or replacement of the work directly […]
The design/build contractor on an expansion of a convention center subcontracted the design and construction work and served as the construction manager on the project. There was a six month delay in structural steel erection and inspection, impacting several subcontractors’ sequences which required schedule changes. Four of the subcontractors issued claims for delay and disruption […]
An $8 mm settlement was reached on a claim involving the design, engineering and testing of the reverse osmosis and pre-treatment systems for a desalination plant. Several claims were filed involving the failure of the dual sand filtration system and improper feasibility assessments. Claimant asserted negligence in design, architectural and engineering services, including the design […]
A claim alleging negligence and design error was issued against a design/build contractor, resulting in a $4.5 million settlement not including high defense costs. Elevated levels of mold were discovered in the HVAC system at a convention center and hotel. The owner demanded remediation and repair to all the HVAC units throughout the hotel to prevent […]
 A claim was settled against a design/build firm for $24 million alleging various defects and deficiencies in a newly constructed printing plant. Initial allegations of damage were $300 million. Problems arose with the concrete, fire protection, electrical, and HVAC systems. The client continues to incur costs to repair the defects. The design/build contractor sought recovery of […]
The RT ECP team frequently publishes in-house articles, reposts relevant news reports and creates educational videos known as "quibinars". For more information or to subscribe, please click on the button below.
SUBSCRIBE TODAYUnfortunately Microsoft is no longer providing support or security fixes for your web browser. RT Specialty values the safety and security of its clients’ data, and as such this site requires the use of a modern web browser. To update your web browser, please see the links below. If you have any questions or would like additional information, please email info@rtspecialty.com or call (312) 784-6001.
![]() |
![]() |
![]() |
![]() |